Bedford Hills 45152-C

Our partner

Proton Construction Corp.

Cost

$2,168,000

Description

Constructive US managed to create a baseline schedule for the Bedford Hills project covering all scope of work along with the required permits. The schedule included the roof replacement of 4 buildings starting with the asbestos abatement and removal of existing roofing system along with temporary salvage of existing mechanical equipment followed by installation & testing of new roofing system. Constructive US assigned the suitable calendar for the project in order not to allow work during winter (December to April) since construction work had to be done while keeping the building watertight.